If you drive Bethel Road often, you have probably passed the field near Goodley Road and wondered when the township's "preserve" will open. On September 24, 2026, Bethel Township announced a $500,000 Pennsylvania Local Share Account grant for the project. The money comes from state gaming revenue and is meant to turn the Shaffer Property into a public preserve with an ADA-accessible trail network, parking, meadow and lawn areas, and a boardwalk connecting neighboring communities. That grant was the last big piece of funding the township had been chasing. With it, outside money covers the land and most of the first phase of construction. The remaining questions are permits, construction timing, and a site whose groundwater and neighbors have already reshaped the plan.
The preserve sits at 1657 Bethel Road in Garnet Valley. According to the township's Shaffer Preserve background sheet, it covers about 20 acres bounded by Bethel Road, Goodley Road, Sarum Farm Lane and Naamans Creek. The Shaffer house and outbuildings are not part of it. Bethel bought the land after negotiations with Dr. Shaffer in December 2021, and grants paid the purchase price of about $577,000.
Two grants covered the purchase. Delaware County awarded $342,667 through its Green Ways program toward buying the parcels at 1645 and 1657 Bethel Road. A January 2022 release from State Rep. Craig Williams reported a $243,800 DCNR grant toward buying about 20 acres along Bethel Road for passive recreation. Those two awards add up to a little more than the township's approximate purchase figure.
Since the purchase, the grants have gone toward building the preserve:
| Source | Amount | Purpose |
|---|---|---|
| DCNR, 2024 round | $354,000 | Loop trails, stormwater, parking, lighting, ADA access |
| PECO Green Region, announced July 2026 | $10,000 | Preserve improvements |
| PA Local Share Account, approved 9/15/2026 | $500,000 | Final design and construction |
| Development grants combined | $864,000 | |
| Phase 1 estimate, November 2025 | $1,369,885 |
The DCNR award appears in the Bicycle Coalition's November 2024 summary of that grant round. The PECO grant was announced on the township's July 14, 2026 Board of Supervisors agenda. The $500,000 award is on the Commonwealth Financing Authority's approved-projects list for its September 15, 2026 meeting, listed as "Shaffer Preserve Final Design and Construction."
The state grant took a while. The November 2025 background sheet lists a $782,460 Local Share Account application from the 2024 round as pending. It says the award had been delayed and the township would resubmit in the next round. The sheet also says the budget was larger than the grant and names the township's recreation fee as one way to cover the difference. The award that came through in September was smaller than that request. Combined, the development grants cover about 63 percent of the Phase 1 estimate.
Before anyone drew a trail, the land already came with rules. The property is under a conservation easement held by the North American Land Trust. The easement dates to 1999 and allows only passive recreation inside it. That's why the plan has no ballfields or courts. Bethel's organized sports fields are at Bethel Community Park.
Within those limits, the current plan includes:
The Goodley Road boardwalk matters for walkers. The township says that entrance serves another 134 properties, plus more if residents connect through the Bethel Springs Nature Trail. For those households, the preserve would be a walk from home, not a drive to a 16-space lot.
A pavilion, fence repairs and an arborist's tree-removal plan are listed as future items and aren't part of Phase 1.
The biggest change between the first design and the current one is the trail. Simone Collins Landscape Architecture was hired in 2022 and held three public meetings in 2023, on April 27, August 24 and September 12. The original design had 1.35 miles of trail. The current design has 0.42 miles, which the township describes as a 68 percent reduction. The township's materials don't explain the reduction. They do show what has changed on the site since engineering moved to Chester Valley Engineers, which presented updates on January 28 and November 20, 2025:
The design changes the township has documented trace to two things, groundwater under the basin and the homes along Sarum Farm Lane. The 0.42-mile trail is a short loop through meadow and woods, smaller than what residents asked for in the township's open space survey. Of the 314 people who responded, 80 percent wanted walking and jogging trails at Shaffer, and 84 percent wanted a walking path.
The November 2025 presentation set a two-step schedule. By the end of that month, plans would go to the Delaware County Conservation District for an NPDES stormwater permit, and to the Conservation District or DEP for the bridge and wetland work. By the end of June 2026, the permits would be in hand and the township would discuss construction timing.
June has passed. The July 14, 2026 supervisors' agenda mentions Shaffer only in the PECO grant announcement. The September 24 grant notice gives no construction start or opening date. The project is designed and mostly funded, and the September grant names "Final Design and Construction" as its purpose. The township hasn't yet announced when construction will start or when the preserve will open.
You can follow along on the township's Shaffer Preserve Plan page, which has the presentations, cost estimate and site plans. Concord Township's Bush Hill Farm, home of the Harvest Festival, has followed the same slow, step-by-step path toward becoming a park.
Bethel's three existing parks are open daily from dawn to dusk:
Jack King Park shows the same issue on a smaller scale. A May 2026 special-meeting agenda proposed replacing its boardwalk sections with a crushed-stone or cinder path, with materials capped at $7,000. The boardwalk replacement had been waiting on a wetland review back in June 2025. The Parks and Recreation Board's June 2026 report said the work would go ahead once site conditions improved. The same report recommended permanent LED lighting for the Adkinson gazebo. Expect sections of the Jack King path to be under construction or recently redone.
If you're driving to any of these on a weekday before December 18, PennDOT has flagger-controlled lane closures on Bethel Avenue between Route 452 and U.S. 322 from 7 a.m. to 3:30 p.m. The township warns of backups. The next township event on the calendar is Lunch with Santa on Saturday, December 5. More on parks and daily life is on our Garnet Valley neighborhood page.
If you own a home near Bethel Road, Goodley Road or Naamans Creek and want to know how a future preserve next door fits into your own plans, The John Bell Team follows projects like Shaffer closely and is glad to talk it through. Request Your Free Home Valuation and we'll start with your street.
Stay up to date on the latest real estate trends.
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact John today so he can guide you through the buying and selling process.