November 19, 2026
In April 2023, a resident of the Concord Hunt development stood up at a Concord Township Council meeting and asked what the planned roundabout on Smithbridge Road would mean for the neighborhood. A council member read the township engineer's answer into the record. The main item left was right-of-way acquisition, and construction was projected to start in summer 2024.
Summer 2024 came and went, and the signal at Smithbridge, Temple and Kirk roads is still there. At council's Nov. 4 meeting this month, township engineer Nate Cline gave a new schedule. PennDOT will advertise the project in January, bids are due Feb. 11, construction starts sometime in summer 2027, and the work should be finished in 2028, according to ChaddsFordLive's report on the meeting.
It would be easy to file that schedule with the earlier ones. One part of it is different, though. Every past target for this project was a forecast. A bid opening is an event, and on Feb. 11 contractors either submit prices or they don't. For Garnet Valley families who drive Smithbridge to the high school twice a day, that is the first date on this project's calendar they can actually check.
The roundabout is one piece of a larger plan. The Delaware Valley Regional Planning Commission lists it as the Smithbridge Road Corridor, MPMS 107642. The plan calls for an 8-foot multi-use trail along Smithbridge Road linking residential neighborhoods to the Garnet Valley School District campuses, intersection work at those campuses, and a roundabout at Temple Road. Earlier descriptions in ChaddsFordLive also included dedicated turn lanes for Garnet Valley High School and a trail from the school to Kirk and Temple roads, ending at a roundabout in place of the current signal.
Here is how the timeline has moved in the public record:
| When it was said | Where | The target at the time |
|---|---|---|
| July 2017 | Delco Times | Corridor work to start in spring 2018 |
| October 2020 | ChaddsFordLive | Construction the following spring, done by fall 2021 |
| FY2023–2026 TIP | DVRPC | Estimated letting date of Nov. 2, 2023 |
| April 2023 | Concord Township Council minutes | Right of way still pending, summer 2024 start |
| May 2026 | ChaddsFordLive | PennDOT to award the bid in early fall |
| September 2026 | ChaddsFordLive | Final filing possibly in October, letting by year-end |
| November 2026 | ChaddsFordLive | Advertise in January, bids Feb. 11, build summer 2027 to 2028 |
The 2017 date was a district-wide hope for the whole corridor. When the Delco Times first reported the partnership between Garnet Valley and Concord, the goal was to ease peak-hour traffic on Smithbridge with turning and stacking lanes for high school traffic, plus sidewalks and trail connections. The 2020 forecast belonged to the specific package that included the roundabout. Everything after 2022 belongs to a project whose drawings were already finished.
The last three rows of that table all come from 2026, and they cover only six months. In May the township expected an early-fall bid award. In September it was still waiting on PennDOT comments. By November it had a January advertisement and a February bid opening. The schedule kept moving this year, but each version came with more specific steps.
In April 2022, Cline told council that the design was "essentially complete" but that progress was slow. He named the reasons, and none of them were about the shape of the roundabout.
Here is what the public record shows standing between finished drawings and a contractor, in the order it came up:
Each step on that list depends on someone outside the township. That explains why the dates kept slipping while the drawings stayed put. Cline's line from 2022 sums it up: "working with PennDOT just takes time."
The historic building in the first item has deep roots on this road. The Concord Township Historical Society runs its museum and headquarters as the Virginia Merion DeNenno History & Educational Center, in the historic Pierce-Willits house at 659 Smithbridge Road. The Society says the center reopened in June 2014. It was renamed in 2009 for Ginny DeNenno's historic preservation work, and the Society's biography of her notes that she lived at the corner of Kirk and Smithbridge roads until the farm there was sold for development in the early 1990s. A building named for a Smithbridge preservationist ended up as a required stop in the review of a modern intersection on the same road.
The 2028 finish makes more sense next to what Serock said in May. In ChaddsFordLive's account of that meeting, she said the work would take about two years because it has to be phased around the school district.
In practice, a two-year job on Smithbridge means at least one full school year of construction on the road the trail is supposed to serve.
Most of the maintenance question is already answered. At the same May meeting, council passed a resolution on maintenance for the roundabout, which hasn't been built yet. Cline called it "a matter of who will take care of what":
The unsettled trail question goes back to how the project started. The 2017 partnership was between the school district and the township, and the trail is the part of the corridor that leads to the campuses.
The cost has shifted over the same years. In 2017, the Delco Times put the corridor project at about $2.1 million, with a federal grant of just under $1.6 million. DVRPC's FY2023–2026 Transportation Improvement Program listed $3.145 million across the project's phases.
The current DVRPC project page shows two construction lines. One is $1.843 million in Congestion Mitigation and Air Quality money in fiscal 2025. The other is $1.055 million in Highway Safety Improvement Program money in fiscal 2026. Together that's $2.898 million for construction.
In 2020, ChaddsFordLive reported that the project was funded by Concord Township, the Garnet Valley School District, PennDOT and DVRPC. With four funders, some of them on fiscal-year programming cycles, the totals shift as the schedule does. The figure that will matter is the one in the bids that come back in February, not any earlier estimate.
For residents, the next few months come down to a short list of checkpoints:
Concord Township Council has given updates on the roundabout at its regular meetings all year, most recently on Nov. 4. Those meetings are the most direct way to follow the project, as they have been for the township's other long-running work, such as the barn-by-barn restoration at Bush Hill Farm.
Until then, Smithbridge Road carries on as usual. Elsewhere on the road, The Coffee Station has opened its third location at 1117 Smithbridge Road, in the building that housed Meghan's Restaurant for 27 years, Delco Today reported. For more on the area around the corridor, see our Garnet Valley neighborhood guide.
If you own a home along Smithbridge or in one of the developments it serves and you're thinking about timing a sale around two years of road work, John Bell can walk you through what buyers in the Garnet Valley school corridor are paying today. Request Your Free Home Valuation and we'll start with your street and the schedule above.
Stay up to date on the latest real estate trends.
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact John today so he can guide you through the buying and selling process.